Excavation works are in full swing at the station box. RC roof of the north cut and cover tunnel has also been cast. Main drive of the 4 TBMs are progressing and should be completed from the end of Q3 2017 onwards.
Excavation works in full swing at the station box |
Tunnelling works towards Upper Thomson. TBM 2 is at the intersection near flame tree park now. |
TBM 1 is about 30% completed and TBM 2 50% completed |
POB beam dismantling along Upper Thomson Road for TBM 1 and TBM 2 drive (Photo: Asiagroup crane, Jan 17) 7th bridge to be demolished under TEL1-3 project |
Excavation works commencing at the south side of the station |
Entrance C excavation to concourse level reached and base slab RC works being prepared |
Casting work |
Roof slab completed at north cut and cover tunnel |
Casting of tunnel wall at north cut and cover tunnel (December 2016) |
No comments:
Post a Comment
Note: only a member of this blog may post a comment.