Sunday, 17 April 2016

Marina Bay Excavation (II)

The roof slab of the station has been fully concreted and excavation for the top-down construction of the station progresses. 2 separate updates taken in March and April have been compiled in this post.


March 8


Casting of the remaining south end of the roof



March 8
April 17 - Completed roof slab
Bored pile works









Assembled gantry crane for the T226 project believed to support the operations of the open face shield rectangular TBM
Completed JTSC open face shield TBM for the linkway tunnel beneath the 2 existing operational lines



Grouting taking place above the North South Line









No comments:

Post a Comment

Note: only a member of this blog may post a comment.