The roof slab of the station has been fully concreted and excavation for the top-down construction of the station progresses. 2 separate updates taken in March and April have been compiled in this post.
March 8 |
Casting of the remaining south end of the roof |
March 8 |
April 17 - Completed roof slab |
Bored pile works |
Assembled gantry crane for the T226 project believed to support the operations of the open face shield rectangular TBM |
Completed JTSC open face shield TBM for the linkway tunnel beneath the 2 existing operational lines |
Grouting taking place above the North South Line |