Saturday, 31 March 2018

Havelock Cast

Structural works are in progress within the station.


Havelock Site

Great World - Tunnelling Completes

RC works are in progress at the station and entrances, with pipe jacking works for the subway beneath Kim Seng Road underway. Both Changi-bound tunnels to Havelock and Orchard have completed, wrapping up tunnelling works for the project.


Breakthrough of Herrenknecht S-946 at Havelock Station on March 27, completing the Mixshield's second and final 500m Changi bound tunnel drive between both stations (Photo: Padraig Higgins, HK)

Friday, 30 March 2018

Orchard Cast (VI)

Structural works for the station, entrance and ventilation structures progresses at the site, with A&A works commencing at the North South Line and ION substructures. Backfilling and site clearing works are taking place around the cut and cover tunnel site in preparations for the SWC staging ground.


Orchard Station