Sunday, 8 October 2017

Shenton Way Excavation (III)

Bored tunnelling works between Marina Bay and Shenton Way stations have completed with the second and final drive of TBM 2 docking at the upper platform of the station. FSC works have commenced for the lower tunnel. The porous geological conditions around the former shoreline beneath Shenton Way has created an ongoing challenge for TBM 1 since its launch in April, which has progressed little since its main drive conversion.

Bulk of the station's structure has reached the under-lower platform level, with a final zone of excavation works due for completion within a month. Excavation and shoring works have commenced at entrance C.


Completion of 144-bored pile linkway between the station, entrance C and Asia Square

Friday, 6 October 2017

Maxwell Cast (II)

The final portion of roof slab across the center zone of the station is being cast. Structure of the station has reached the concourse and upper platform levels at the south and north end respectively.


T223 Maxwell Station

Thursday, 5 October 2017

Outram Park Excavation (III)

Excavation works across the network of new unpaid and paid linkway are progressing across the site. The project's second and final TBM relaunch took place at the end of Q3 for the Changi bound tunnel drive towards Havelock.


T222 Outram Park