Tuesday, 28 February 2017

Woodlands Cast (II)

Casting works for the station have progressed up to the concourse slab.


Excavation & strutting at crossover tunnel

Monday, 27 February 2017

Woodlands North Cast (III)

Casting work continues at the Woodlands North site. The platform level of the station is completed and formwork is being propped for the casting of the concourse level. Structure of the north crossover tunnel is forming up.


South crossover tunnel structure nearing completion

Tuesday, 31 January 2017

January Tunnel Progress

The 36th and third last TBM for the line was lowered down the Great World launch shaft earlier this month, with several more bored tunnels having been completed since.


TEL1&2 Tunnel Chart, January 2017
TEL3 Tunnel Chart, January 2017