Sunday, 11 December 2016

Springleaf Excavation (IV)

Excavation works are ongoing at nearing completion at the station box.


Springleaf Station

Saturday, 10 December 2016

Facility Building Backfill

Superstructures for the escape shafts are coming up as the TBM main drives are underway. TBM 1 and 2 are now beneath the Seletar Expressway bounded for the RTS Facility Building,  The first breakthrough of TBM 3 and 4 are expected by the next quarter.


Dismantled gantry crane, backfilling and RC works for the facility building

Friday, 9 December 2016

Mandai Depot - Trackwork Begins

Commencement of the line's largest system-wide contract, led by CTCI for the design, supply, construction, testing and commissioning of trackwork and third rail system, took place this quarter with the staging ground prepared at the Mandai Depot. This is the second back-to-back trackwork project awarded to the Taiwanese contractor, with a smooth transition of resources expected from the recently completed Downtown Line 3.


Structure for the stabling yard, bus parking deck and perimeter wall mostly completed