Saturday, 10 September 2016

Tagore Cast (III)

TBM C was relaunched in July. The removal of the temporary rings and reaction frame at the lauch shaft last month completes the TBM's conversion to its main drive. TBM B is now halfway through its tunnel drive to Springleaf and under the Seletar Expressway. The concourse slab at Tagore has been cast.


TBM B and TBM C2 progress as of September 8

Thursday, 8 September 2016

Wednesday, 7 September 2016

Facility Building Cast (II)

The RTS facility building is progressively being constructed upwards. Main drives are underway across all 4 TBMs.

TBM 3 and TBM 4 progress from Sembawang Airbase to RTS Facility Building
TBM 1 and TBM 2 progress from Springleaf Station to RTS Facility Building
RTS Facility Building