Friday, 30 June 2017

Upper Thomson Excavation

D-walling works for the station was completed earlier this quarter and the associated silos have been dismantled. Bored piling works for the station's foundation are taking place at the south side of the station, while excavation works on the north end has reached the concourse level.


Bored piling works around entrance D

Thursday, 29 June 2017

Bright Hill Excavation (II)

Excavation works at the station box are ongoing to the platform level, with the concourse slab completed. The Woodlands bound tunnel to Mayflower has presumably been completed by TBM 4, and the remaining 3 TBMs are anticipated to complete by the next quarter.


Ground improvement works at the extracted H-pile foundation of the former POB along Upper Thomson Road

Wednesday, 28 June 2017

Mayflower Cast (IV)

Structural works for the station and entrances are largely completed. A realignment of Street 11 has taken place for the construction of the underpass link from the station to entrance D.


Basic structure completed at entrance D & realignment of AMK St 11 for the remaining subway construction