Construction of the roof slab is taking place and is midway completed at the Great World station. Excavation works have commenced at the north end of the station, as well as the subway to River Valley road.


T220 Great World site

Thursday, 29 September 2016

Orchard Cast (II)

D-walling works for the project have been fully completed at the cut and cover tunnel ahead of schedule and excavation works have commenced there. Basement casting of the concourse slab is taking place at the station box. A major traffic realignment is being prepared at the Orchard/Paterson intersection for the underpass works.


Completed roof slab at Orchard station

Tuesday, 27 September 2016

Orchard Boulevard Excavation

Top-down construction of the Orchard Boulevard Station have commenced with excavation works reaching the roof slab. Concreting works will take place in the next quarter.