Monday, 5 September 2016

S-893 Reassembly

Having completed the Changi Bound tunnel from LS2 to Woodlands, the re-assembly of S-893 (TBM 1) is taking place at LS1 for the RT3 tunnel drive to Woodlands Station. The TBM is expected to launch next month and breakthrough by mid-2017. TBM 3 has been retrieved from Mandai Depot and is held at the surface of LS2, awaiting to be reassembled for the Changi bound tunnel drive to Woodlands South Station.


Launch Shaft 1/ ES1

Sunday, 4 September 2016

Woodlands South Excavation (II)

The diaphragm wall for the southern zone of the station box and entrance A have been completed and excavation works are underway here. Bulk excavation works for the station are in progress at the completed north zone. The final D-walling works for the project are in progress at entrance C.


Shoring works at entrance A

Saturday, 3 September 2016

Woodlands Excavation (V)

Bulk excavation works for the station box have reached the S5 layer and is nearing the formation level. Bored pile works are still being done at the crossover cut and cover tunnel.


T203 Woodlands Station