Tuesday, 26 August 2014

ULS - Preparations to Divert

Works are in full swing for the staging of one of the biggest road diversions to be implemented along the corridor of the Thomson Line. Road surfacing has begun for the new Upper Thomson Road that will swing round the existing road which will be excavated up for the Upper Thomson Launch Shaft (ULS). The new POB has already been launched up this week.

The diversion will take place on Sunday, September 14 and would last throughout the entire duration of the tunnelling phase of the project, estimated to be completed in 2019.

August 29
Northbound road has completed surfacing
Roof of the new POB is almost completed

Saturday, 26 July 2014

Tunnel & Track Chart

With the confirmation of the civil contractors from the announcement yesterday, the tunnel chart has been updated. Alongside with the announcement of the trackwork contractor, we reveal the schematic track diagram.

Tunnelling works for the Thomson Line is scheduled to commence around mid 2015. Several announcements regarding the procurement of the 30+ TBMs varying between EPB and slurry types can be expected from the manufactures in the coming months.

Abbreviation breakdown:
SBAB - Sembawang Airbase
5XO - TS05 Crossover
ULS - Upper Thomson Launch Shaft
GBME - Gardens By the Bay - Marina East


Tunnel Chart for Stage 1 and 2
Tunnel Chart for Stage 3
Schemaic track diagram subdivided into the 4 civil teams