Excavation works for the station have reached the mezzanine level and are proceeding down to the platform level. The concourse slab has been fully cast, with RC works taking place at the mezzanine slab and mezzanine service slab. Preliminary works have started for entrance E at the Downtown Line structure which will form the basement 1 link to the TEL concourse.
Stevens Station |
Plan view of station |
D-wall at Entrance B completed, sheet piling works in progress |
Excavation works at station |
Excavation opening 4 |
Structure progress from top to bottom (Basement roof slab, Concourse slab, Mezzanine slab, Mezzanine services slab) |
Excavation works progressing down to the platform level |
Excavation opening 3 |
Preparations for excavation works down to mezzanine service level |
Formwork for concourse wall casting |
Completed concourse slab |
Skinwall casting at concourse level |
Excavation opening 2 |
RC works at mezzanine slab |
Concourse paid area |
Excavation opening 1 |
Excavation at Entrance A and vent structure 1 |
Entrance A at concourse level |
Excavation works for ventilation structure at entrance A down to mezzanine level |
Commencement of works at Entrance E at DTL station |
Hoardings surrounding the front facade of the DTL with preliminary diversion and alteration works being carried out to the DTL structure |
Escalator Shaft base slab casting works |
Entrance C & D site |
RTBM dismantled |
Entrance C staircase cast |
Completed underpass structure with TBM dismantled |
Cutterhead interface at the escalator shaft |
T216 Evans Road storage site at the former DTL site office |
Storage of replacement shield for TBM 3 for the line's final TBM drive between Dalvey LS and Stevens Station next year |
Launch shaft 10 |
TBM 1 at Ring 478. TBM 2 at Ring 472 |
MPS (LS10) to STV Station TBM progress |
STV to NPR TBM progress. TBM 3 at R268, TBM 4 at R402 (beneath Nassim Road) |
No comments:
Post a Comment
Note: only a member of this blog may post a comment.