The full face rock conditions experienced by the final 2 EPBMs from Springleaf have significantly hindered the progress over the last quarter with an average advancement rate of a single ring building per day. TBM 1 is about 30 rings from breakthrough and should complete within a month's time.
Tower crane erected to facilitate the RC works of the facility building superstructure |
No comments:
Post a Comment
Note: only a member of this blog may post a comment.