Excavation of LS3 have commenced within the Shenton Way station, of which the bored pile works are still progressing. The roof slab is being prepared for sequential casting and rebar installation is in progress. TBM 2 has commenced its initial drive at LS4 following the commencement of tunnelling works earlier this month.
Top-down view of the station box with its roof slab progressively being constructed concurrent with the bored pile foundation works |
Excavation works at launch shaft 3 |
Excavation works at MC street for EWL tunnel underpinning |
Rebar works for roof slab |
Bored pile works |
Driving of king post |
Eventual dismantling of the bentonite silos following the completion of the earth retaining wall & foundation works |
Connection of backup gantries to TBM 2 |
Launch of TBM 2 at the start of June |
Photo credits: Chalermdech |
Initial drive has commenced |
TEL3 Tunnel Chart, June 2016 |