Monday, 28 December 2015

Piling at Havelock (V)

Piling works continue at the Havelock station. Excavation is ongoing for the launching shaft for the rectangular TBM as well as the adjacent entrance E. Preparations are underway for the realignment of Havelock Road which will be implemented around February.


Excavation of the launch shaft and entrance E

Fissure grouting taking place ahead of the launch shaft

On-site molding and casting of the precast tunnel segments (background) due to its massive and irregular size for transportation
Preparations to divert Havelock Road
Preparations to divert Havelock Road


Piling at Entrance D
Havelock station