The project team at Shenton Way has closed the section of Park Street behind Asia Square to facilitate the Diaphragm wall works for the station box. Several modifications have been made to Marina View to maintain traffic access to Tower 2 of Asia Square.

Excavation of the temporary culvert beneath the linear park is complete, while works are still on going at the southern section near the interface of the station box. D-walling works continue at the launch shaft.


Closed section of Park Street
Modifications to traffic access at Tower 2
Temporary monsoon box culvert


Station box
D-walling at the launch shaft
Park Street will be extended down from McCallum St through the location of the demolished Golden Bridge

Tunnels that will bore down from Marina Bay to Shenton Way station