Tuesday 21 April 2015

Marina South - Deep Cement Mixing (II)

The cut and cover tunnel to Gardens by the Bay which have been hoarded up, now elongates the worksite boundaries of the T227 project parallel to the Marina Coastal Expressway. Deep Cement Mixing is taking place along the C&C site, in addition to the existing ground improvement works being done at the Marina South Station.



Southern boundary of the C&C tunnel site; Aerial view of the T227 project
Northern boundary of the C&C tunnel site
Interface between C&C and Marina South station (MRS) along Marina Boulevard
Pipe piles
DCM works at MRS
DCM works at MRS
DCM works at MRS
DCM across Central Boulevard

No comments:

Post a Comment

Note: only a member of this blog may post a comment.