Today the Land Transport Authority announced the award of contract T251 for the supply of electric trains for the Thomson (TSL) and Eastern Region Lines (ERL). A total of 91 units will be procured for the two lines under the contract, awarded to the consortium of Kawasaki Heavy Industries, CSR Qingdao Sifang Co. Ltd. and Kawasaki Heavy Industries (Singapore) Pte. Ltd.
A render of the train to be procured from Kawasaki - CSR Qingdao Sifang for the TSL & ERL |
Under stage 1, 9 trains will be used in operations. For stage 2, a further 20 trains will be available, bringing the total to 29. At stage 3, there will be 24 trains delivered, for a total of 53 trains during the initial stages of the TSL operation. As the TSL and ERL are expected to operate as a single line, a further 38 trains will be procured, bringing the total number of trains to 91.
Indicative make up of the Kawasaki trains. |