Thursday, 21 January 2016

January Tunnel Progress

TEL1/2 Tunnel Chart, January 2016
(T206 - Reception tunnels emerge between the mainline tunnels in actuality, however shown otherwise on the chart for simple illustration)

Contract T202
Excavation of the Changi-bound tunnel is advancing at a slow pace and 2 cutterhead interventions have been performed since the launch of the TBM back in December. It's sister TBM is slated to commence mining on the Woodlands-bound tunnel by the end of this month.

Changi Bound Tunnel, T202 WDN-WDL (Dec 28)

Wednesday, 13 January 2016

Piling at Gardens By The Bay

The diaphragm wall for the Gardens By The Bay station has been completed and bored pile works on the foundation is taking place concurrent with the jet and fissure grouting. The launch shaft has been excavated down to about 9m now, with the realigned Marina Gardens Drive running above the decking.

Deep soil mixing activities continue along the tunnel route between the Marina Barrage and Gardens by the Bay, while construction of the diaphragm wall at the GBME retrieval shaft across the channel progresses.


Diverted Marina Gardens Drive for the pedestrian subway construction, scheduled for realignment by early 2017

Monday, 11 January 2016

Marina South Excavation

Excavation has commenced at the Marina South station and launch shaft, while piling works progress southwards for the cut and cover tunnel. Deep cement mixing activities continue along the tunnel route towards Marina Bay station.