Thursday, 6 October 2016

Upper Thomson - TBM 3 Assembly

The third TBM for the T212 project was lowered down the Upper Thomson Launch Shaft today following shipment delays. This is the 34th TBM to be lowered for the entire Thomson Line project (C1-C4), and also the last single-drive TBM to be launched. The JTSC Slurry TBM will undergo assembly works within the launch shaft and commence excavation on the 1.36km Woodlands Bound tunnel from the ULS towards Caldecott station by year end.

Collaborating with the tunnel team, the lowering process was captured over a span of 30 hours.


TEL 1/2 Tunnel Chart, September 2016
Tandem lifting of tail shield

Tuesday, 4 October 2016

Outram Park Cast (III)

Completion of the last zone of roof slab took place concurrent with the demobilization of the D-wall grabs and ancillary silo & slurry equipment in August. Bulk excavation works are now underway at the Outram Park station.


Bulk excavation works across the Outram Park station

Sunday, 2 October 2016

Piling at Havelock (VI)

SBP works continue at Havelock station. Tunnelling works for the rectangular TBM which were envisaged by the project team to have been completed now, are only midway through with 61 segments jacked thus far.


Preparations for the installation of R61 at the Havelock launch shaft