Excavation has commenced at the Marina South station and launch shaft, while piling works progress southwards for the cut and cover tunnel. Deep cement mixing activities continue along the tunnel route towards Marina Bay station.
Monday, 11 January 2016
Sunday, 10 January 2016
Marina Bay Excavation
Saturday, 9 January 2016
Shenton Way D-walls (IV)
The diaphragm wall at the Shenton Way station is nearly completed, and construction of the bored piles as well as grouting is being carried out in tandem. STEC have constructed the TBM muck pit and commissioned 2 gantry cranes adjacent to the Marina Bay launch shaft while awaiting possession of the launch shaft which has yet to be handed over by the Taisei team.