Monday, 11 January 2016

Marina South Excavation

Excavation has commenced at the Marina South station and launch shaft, while piling works progress southwards for the cut and cover tunnel. Deep cement mixing activities continue along the tunnel route towards Marina Bay station.



Sunday, 10 January 2016

Marina Bay Excavation

Construction of the diaphragm wall is nearing completion at Marina Bay and excavation of the station box has commenced.



Saturday, 9 January 2016

Shenton Way D-walls (IV)

The diaphragm wall at the Shenton Way station is nearly completed, and construction of the bored piles as well as grouting is being carried out in tandem. STEC have constructed the TBM muck pit and commissioned 2 gantry cranes adjacent to the Marina Bay launch shaft while awaiting possession of the launch shaft which has yet to be handed over by the Taisei team.