Saturday 9 January 2016

Shenton Way D-walls (IV)

The diaphragm wall at the Shenton Way station is nearly completed, and construction of the bored piles as well as grouting is being carried out in tandem. STEC have constructed the TBM muck pit and commissioned 2 gantry cranes adjacent to the Marina Bay launch shaft while awaiting possession of the launch shaft which has yet to be handed over by the Taisei team.














Ground improvement works under McCallum St and protection of EWL tunnels at Robinson Road





Setting up of gantry cranes adjacent to the launch shaft
Completion of muck pit adjacent to the shaft



Photo cr: Chalermdech (Dec 2015)

Fissure grouting along the tunnel route

No comments:

Post a Comment

Note: only a member of this blog may post a comment.