Completion of the last zone of roof slab took place concurrent with the demobilization of the D-wall grabs and ancillary silo & slurry equipment in August. Bulk excavation works are now underway at the Outram Park station.
| Bulk excavation works across the Outram Park station |
| Excavation works at north launch shaft |
| Final zone of completed roof slab |
| South launch shaft |
| Backup gantries |
| Tunnel segments |
| Preparations for TBM 2 launch (left) / Initial drive underway along TBM 1 (right) |
| Bored pile works |
| Shoring works at SGH entrance (together with closure of HSA carpark) |