Bulk excavation works continue at the Gardens By The Bay station.
Sunday, 26 June 2016
Saturday, 25 June 2016
Marina South Excavation (III)
Friday, 24 June 2016
Marina Bay Cast
RC works for the concourse slab are in progress at the Marina Bay station, while piling works commence for the interchange linkway to the North South Line. Sheares Avenue have opened between Maxwell Road and Central Boulevard, providing an interim linkage within the restricted zone of the CBD. The permanent road will be realigned towards the end of the project, and will be served by Entrance B and 2 ventilation buildings under the TEL project.
| Opening of Sheares Avenue by the T226 team |
Subscribe to: