More About Us

Saturday, 16 March 2019

Stevens - Excavation Completes

Excavation works for the station box are largely completed down to the paid linkway level, with the dismantling of the temporary earth retaining structural system commencing concurrently. Architectural works for certain portions of the concourse level have started ahead of the overall station BSC due to the delay in the project timeline.

The opening of TEL3 is currently being dragged by the progress of the station, which at present estimate is likely to be delayed by up to 6 months.

TEL3 Tunnel Progress, March 2019. The final TBM 4 is projected to breakthrough at Napier by the middle of Q2.
Stevens Station

Entrance B bottom up excavation

Entrance A


Architectural cladding brackets and 2nd coat of paint along the Concourse level 
Cutting of station D-wall at C919 DTL2 D-wall interface

Station mezzanine level
Under platform level
Under platform level (bored tunnels from T215)
Dismantling of struts at paid linkway level



Under platform level
Bored tunnel from LS1

Concourse level unpaid linkway to entrance B
Escalator shaft


Entrance C&D site





Whitley Road POB A&A works and new bus stop


Reinstatement of LS10 site at Mount Pleasant




LS1 site

CP2 site

CP2A site

Underpinning works to Block 1 at Botanic Gardens View. Progress of TBM 4 is halted at the site as the piles of the apartment building were found to be deeper than what was initially projected during the design stage, and is now in the path of the Changi Bound tunnel.

Reinstatement of Evans Road storage site

No comments:

Post a Comment

Note: only a member of this blog may post a comment.