More About Us

Tuesday 16 June 2015

Piling at Mayflower (IV)

Piling works at the Mayflower Station are now about 60% completed. The third traffic diversion along Avenue 4 was implemented earlier this month. The realigned road to the east now allow for piling to be done on the west side of the station box. The diversion is envisaged to last for 3 months. Grouting is taking place on the south side of the station as well.


Stage 3A Traffic Diversion




Grouting works





No comments:

Post a Comment

Note: only a member of this blog may post a comment.