Excavation works have commenced on the north face of the station box. The outline of the launch shaft at the south end of the station is evident too, and we can expect excavation of the shaft to commence by the third quarter of this year. The linkway to the Calrose entrance seems to have completed excavation to the formation level where 3 layers of struts have been installed.
D-walling works continue at the 5XO crossover site along Ang Mo Kio Avenue 4.
|
Lentor Station |
|
D-walling at 5XO |
|
Lentor station |
|
Shoring system of the linkway |
|
Ground improvement works by T208 along the TGR-LTR tunnel route in the background |
|
5XO |