More About Us

Friday, 3 July 2015

Piling at Bright Hill (III)

Piling works continue in full swing at the north and south cut and cover tunnels, in addition to the continual drain diversion works at the Bright Hill Station. Penta Ocean has begun preparatory works for the reconstruction of the Pedestrian Overhead Bridge at Ang Mo Kio Avenue 3. The new bridge is expected to be up by the end of the year, prior to the TBM launching. The T211 team is also conducting ground improvement works near Thomson View condo for the south tunnel drives to Upper Thomson.


Hoardings erected for the replacement POB at Avenue 3
Piling works at the north C&C tunnel / Drain diversion works






South C&C tunnel







No comments:

Post a Comment

Note: only a member of this blog may post a comment.