Thomson Line Construction

8 Year documentation on the making of the Thomson Line

More About Us

▼
Friday, 29 December 2017

Gardens By The Bay - Tunnelling Completes

›
Tunnelling works for the T228 project have completed ahead of schedule, with the Hitachi Zosen EPBM breaking through the station d-wall fro...
Thursday, 28 December 2017

Marina South Cast (IV)

›
RC works for the internal structure of the station continues up to the roof slab. The TBM has completed the Woodlands bound drive to Marina...
Wednesday, 27 December 2017

Marina Bay Excavation (V)

›
Excavation works continue towards the formation level at the lower underplatform level. JGP works are taking place beneath the NSL and CCL ...
‹
›