RC works for the internal structure of the station continues up to the roof slab. The TBM has completed the Woodlands bound drive to Marina Bay and reassembly works for the Changi bound drive have begun with the dismantling of the backup gantries & assembly of the heavy lift crawler crane on site. The relaunch of the TBM is scheduled next quarter - the 2nd last to be facilitated along the TEL1-3.
Marina South station |
Grouting works at entrance B |
Cover for cutterhead and tail shield exposed |
Launch shaft. Backup gantries being removed (left) from the completed Woodlands bound tunnel |
Assembly of heavy lift crane |
Delivery of counterweights |
RC columns up to the roof slab |
Roof slab completed between GL5-10 & S1 struts removed |
Excavation works completed to platform level around GL12-15 at ventilation area. |
Linkway to entrance D & vent shaft 4 |
Rebar installation for internal walls at the linkway |
Station overview |
Cut and cover tunnel site |
Backfilling works progresses over completed roof slab |
De-strutting works |
Removal of king post & backfilling to ground level |
Temporary staging access structure for trackworks |
Portal access to the Woodlands & Changi bound trackway at the cripple siding tunnel |
Pipe pile construction at the crossover tunnel interface at T228 |