Casting of the internal structure within the station is ongoing concurrent with the excavation and RC works at the unpaid linkway. Excavation works for TBM 1 has resumed with a further 100 rings advanced this quarter. In view of the lost time caused by the challenges at McCallum St, the project team is re-using TBM 2 to complete the Changi bound tunnel towards Maxwell. The TBM commenced mining works today, making it the 3rd last TBM relaunch along TEL1-3.


Shenton Way Station
MC street 
TBM 1 at 210 rings (40% completed) beneath Cecil St
Launch shaft
TEL3 Tunnel Chart, December 2017
TBM 2 relaunched for the third time for the Changi bound tunnel drive to Maxwell
Backup gantries for the TBM extending onto the station upper platform slab
Station box
Falsework at the lower platform supporting the upper platform casting

Plantroom level internal wall casting
Excavation works at linkway level
Entrance B

Linkway to Asia Square 2



Linkway to entrance C
Completed RC portion


Filling works at temp monsoon canal


LS4 site at Marina Bay demobilized by T225 prior to handover on Dec 29