Casting of the internal structure within the station is ongoing concurrent with the excavation and RC works at the unpaid linkway. Excavation works for TBM 1 has resumed with a further 100 rings advanced this quarter. In view of the lost time caused by the challenges at McCallum St, the project team is re-using TBM 2 to complete the Changi bound tunnel towards Maxwell. The TBM commenced mining works today, making it the 3rd last TBM relaunch along TEL1-3.
Shenton Way Station |
MC street |
TBM 1 at 210 rings (40% completed) beneath Cecil St |
Launch shaft |
TEL3 Tunnel Chart, December 2017 |
Backup gantries for the TBM extending onto the station upper platform slab |
Station box |
Falsework at the lower platform supporting the upper platform casting |
Plantroom level internal wall casting |
Excavation works at linkway level |
Entrance B |
Linkway to Asia Square 2 |
Linkway to entrance C |
Completed RC portion |
Filling works at temp monsoon canal |
LS4 site at Marina Bay demobilized by T225 prior to handover on Dec 29 |