Bored tunnelling works between Marina Bay and Shenton Way stations have completed with the second and final drive of TBM 2 docking at the upper platform of the station. FSC works have commenced for the lower tunnel. The porous geological conditions around the former shoreline beneath Shenton Way has created an ongoing challenge for TBM 1 since its launch in April, which has progressed little since its main drive conversion.
Bulk of the station's structure has reached the under-lower platform level, with a final zone of excavation works due for completion within a month. Excavation and shoring works have commenced at entrance C.
Completion of 144-bored pile linkway between the station, entrance C and Asia Square |
Strutting of S1 against the sheet pile at entrance C |
Backfilled temporary monsoon canal |
Station site |
Acoustic shed completed over LS3 |
Works at MC street |
TBM 1 Main drive towards Maxwell |
Excavation works beneath the upper platform level |
Formwork at the lower platform level |
Breakthrough of TBM 2 Changi Bound tunnel from Marina Bay at SHW Upper Platform on 26 Sep (Photo: T225 Charlie) |
Retrieving the TBM |
TEL3 Tunnel Chart (Sep 2017) |
LS4 at Marina Bay |
Concrete pump for the FSC works at the lower tunnel |
View of the completed Changi bound tunnel from LS4 at Marina Bay |
Installation of concrete feed pipe for First Stage Concreting works along the Woodlands Bound tunnel |
FSC works underway (Photo: T225 Charlie) |