More About Us

Thursday 5 October 2017

Outram Park Excavation (III)

Excavation works across the network of new unpaid and paid linkway are progressing across the site. The project's second and final TBM relaunch took place at the end of Q3 for the Changi bound tunnel drive towards Havelock.


T222 Outram Park
Unpaid link excavation



HSA entrance



New paid link construction between EWL and NEL (EWL interface)

New paid link between EWL and NEL (NEL interface)



New paid link between NEL and TEL (NEL interface)
Launch shaft to Maxwell demob
Excavation works at station





Launch shaft to Havelock
TBM 4 (TBM 2 relaunch) on initial drive along Changi bound tunnel


No comments:

Post a Comment

Note: only a member of this blog may post a comment.