Excavation works are nearing the formation level beneath the S7 level and should complete by the end of the year. The excavation works for entrance D have also commenced, the last of the 5 entrances to be constructed.
Havelock Station fully strutted down to the formation level in preparations for the bottom-up construction |
Casting of Upper Concourse slab and external walls at entrance A |
Rock excavation works below S7 strut layer |
Hoisting of excavated materials via the mobile crane |
Subway to entrance B |
Telescopic excavation |
Entrance B |
Entrance C |
Commencement of excavation and shoring at entrance D |
Former RTBM site demobilized |
Entrance E |