Tunnelling works for the T206 project are wrapping up with 8 of the 10 bored tunnels completed. Cross passage excavation and the first stage concreting works are taking place within the tunnels. Structural, fittings and trackworks are progressing at the depot.
Stabling Yard nearing structural completion |
Rail administration building cast |
Structure for the manual trainwash completed |
RC works for the automatic trainwash nearly completed (right) |
Trackwork progress leading to the locomotive workshop |
Fitting works at substation and permanent way workshop |
RC columns for main workshop completed, structural steel roof work being carried out |
CTCI staging ground |
Load center structure completed |
Wastewater treatment & ancillary building |
RC works for tunnel portal and ventilation fan |
Breakthrough of TBM 3 at Mandai Depot in January, completing the Reception Tunnel 1 (RT1) |
Sembawang Airbase |
Initial drive of TBM 5 for the RT2 drive |
Balance segments for TBM 5 |
Realignment of Woodlands Ave 12 at ES2 completed |
Third replacement shield for TBM 4 |
Dismantling works for TBM 4 being done at the completed Changi bound tunnel towards WDS |
The third drive will be done for the parallel Woodlands bound tunnel (right) by the 2nd quarter of this year |
S-893 drive towards Woodlands on the RT3 tunnel presumably completed with the launch shaft cleared with slurry pipes and tunnel segments |
Dismantling of the STP should be underway in due course |