More About Us

Tuesday 28 February 2017

Woodlands South Excavation (IV)

The roof slab for the entire station is now completed, with filling works in progress prior to the start of bulk excavation on the south side. Bottom up excavation works for entrance A and C are completed and commencing respectively. Rock blasting works are being done at the concourse level and Entrance B.


Roof slab completed at south zone
De-strutting and filling works at station roof
Excavation pit

Hacking of boulders beneath roof slab (photo: LTA)
Formation level reached at entrance A & RC works for base slab in progress/ Concourse slab cast midway at Entrance B


Entrance C bottom up construction
Excavation & strutting commencement at entrance C

No comments:

Post a Comment

Note: only a member of this blog may post a comment.