More About Us

Tuesday 31 January 2017

January Tunnel Progress

The 36th and third last TBM for the line was lowered down the Great World launch shaft earlier this month, with several more bored tunnels having been completed since.


TEL1&2 Tunnel Chart, January 2017
TEL3 Tunnel Chart, January 2017
T219: Completion of Herrenknecht EPBM S-963 Woodlands bound between Orchard and Orchard Boulevard on Jan 20
T220: Lowering of Slurry TBM S-946 at the Great World south launch shaft






Great World photo credit: Joey Yap

No comments:

Post a Comment

Note: only a member of this blog may post a comment.