Casting of the base slab is progressing at the station box. The base slab is completed at Entrance C, and excavation of the adjacent subway has started. Initial drive of the TBM is presumably completed.


Gardens By The Bay Station
Ground improvement works ahead of TBM
Entrance C works
Base slab cast for Entrance C beneath former road
Commencement of subway excavation to Ent C

Initial drive operating on Woodlands bound tunnel

Casting of base slab

Reinforcement for base slab (center zone)

Base slab completed (first zone)


GBME Shaft (Commencement of T302 works seen in the background)
Formation level reached/ excavation completed