Casting of the base slab is progressing at the station box. The base slab is completed at Entrance C, and excavation of the adjacent subway has started. Initial drive of the TBM is presumably completed.
Gardens By The Bay Station |
Ground improvement works ahead of TBM |
Entrance C works |
Base slab cast for Entrance C beneath former road |
Commencement of subway excavation to Ent C |
Initial drive operating on Woodlands bound tunnel |
Casting of base slab |
Reinforcement for base slab (center zone) |
Base slab completed (first zone) |
GBME Shaft (Commencement of T302 works seen in the background) |
Formation level reached/ excavation completed |