More About Us

Monday, 12 December 2016

Tagore Cast (IV)

Casting of the concourse and platform structures are ongoing at Tagore.

TBM B Progress - R504 (706m, 64% completed)
TBM C2 Progress - R367 (514m, 47% completed)


Tagore C&C tunnel

Concourse slab cast between Grid lines 4.5-12




No comments:

Post a Comment

Note: only a member of this blog may post a comment.