Excavation works are in full swing at the station box, with varying progress between the concourse and plantroom level (B2/B3). Excavation of LS3 is still in progress, and LS4 is being handed back to Taisei for the upper tunnel slab casting works.
Installation of gantry cranes for top-down construction of the station |
Casting works |
Excavation works to concourse level |
Excavation to plant room level (B3) |
LS3 |
Excavation of LS3 to S3 layer |
Ground improvement works and preparations for EWL underpinning excavation works at McCallum St |
TBM bearing and internal components being dismantled |
First tunnel completed between MRB and SHW |
Handover of LS4 back to T226 for Changi bound tunnel slab casting |
Replacement TBM stored on site |