Bulk excavation works for the NSL and CCL linkways are underway. The transfer level (B3) has been cast at the station and excavation works are progressing to the upper platform level.
Excavation of Circle Line linkway |
CCL unpaid link excavation completed |
CCL paid link excavation at S3 layer |
Excavation of North South Line linkway |
S2 installation in progress |
Excavation works proceeding to S3 level |
Adit tunnel construction |
Station construction |
Transfer level RC works (M&E service room area) |