More About Us

Monday 7 March 2016

Tagore Cast (II)

The completion of the first bored tunnel for the Thomson Line is coming up within the T208 project. The drive executed by TBM C for the northbound tunnel between the Tagore C&C and Lentor Station is over 90% completed. Maintaining an advance of an average of close to 8 rings per day since the start of the year, excavation of the tunnel is envisaged to complete by the middle of March.

The replacement cutterhead and TBM shield for TBM C has already been positioned at the surface of the north launch shaft in preparations for the second drive towards Springleaf.


French secretary of state for transport Alain Vidalies visiting the NFM TBMs at the Tagore C&C tunnel site in February (photo: NFM)

TGR-LTR tunnel progress for TBM A and TBM C
Receiving end of the TBM at Lentor which is still in the midst of the diaphragm wall construction




No comments:

Post a Comment

Note: only a member of this blog may post a comment.