More About Us

Tuesday, 8 March 2016

Lentor D-walls (II)

The next stage of the diaphragm wall construction is beginning as the completed zone backfills and Lentor Drive gradually shifts back over the completed roof slab. The realignment of the intersection at Yio Chu Kang Road was carried out earlier this quarter and sheet piling works for the entrance at Calrose have begun.


Realigned YCK road over the completed underpass structure












Waterproofing works for the roof slab
Backfilling and destrutting over the completed roof slab zones





The diaphragm wall of 5XO has been completed and bulk excavation is underway across the entire structure












No comments:

Post a Comment

Note: only a member of this blog may post a comment.