Assembly works for the Herrenkencht TBM have commenced at the Napier launch shaft with the both shields lowered down over the last past 2 days. Dual drives will be performed by the TBM for the twin tunnels to Orchard Boulevard, with the lower Woodlands bound tunnel to commence first by the end of this quarter.
|
Cutterhead and assembly of the heavy-lifting Terex crane in the background |
|
Settlement survey prior to the heavy lifting |
|
Lifting of the tail shield on Feb 4 |
|
Lifting of the front shield on Feb 5 |
Photo credits: Mahesh Shelke, David Min, Jay