2 piling machines are currently executing bore pile works at the site of the RTS Facility Building. Further north at the escape shaft, the circular earth retaining structure of the shaft seems to have completed and a mini gantry crane has been assembled. Due to the proximity of the escape shaft within the approach of runway 04 at Sembawang Airbase, the shallow gantry crane will facilitate lifting works at the shaft opening in place of a traditional mobile crane.
Shimz's site office for T207 at the north end of the Springleaf site overlooking the future launch shaft that will be handed over to them |
Piling at RTS Facility Building |
Prefabricated rebar for bore pile |
Escape Shaft |