Friday, 29 September 2017
Orchard Boulevard Excavation (III)
›
Excavations works have reached the formation level, with commencement of rebar installation at the underplatform level. Orchard Boulev...
Wednesday, 27 September 2017
Napier Excavation (III)
›
The relaunch of TBM S-930 at the Napier launch shaft for the Changi bound tunnel drive towards Orchard Boulevard took place earlier this mo...
Monday, 25 September 2017
Stevens - RTBM Assembly
›
Assembly works are in progress for the second launch of the compressed-air Rectangular TBM along Whitley Road. The TBM has been reused foll...
‹
›