Thomson Line Construction

8 Year documentation on the making of the Thomson Line

More About Us

▼
Friday, 21 April 2017

Gardens By The Bay Cast (II)

›
Casting of the permanent structure at the station is progressing at varying levels, with portions of the platform and tunnel walls along bo...
Thursday, 20 April 2017

Marina South Cast (II)

›
Casting of the station has reached the concourse level, while portions of the C&C tunnel roof have been completed. Overview of the ...
Wednesday, 19 April 2017

Marina Bay Excavation (IV)

›
Excavation works have presumably reached the upper platform level and is progressing down to the lower platform. Commencement of sho...
‹
›