Saturday, 5 November 2016

November Tunnel Progress

›
Tunnelling works for the line have been ongoing for 15 months now. 11 bored tunnels have been completed. TEL1/2 Tunnel Chart, November...
Friday, 14 October 2016

Gardens By The Bay - TBM Assembly

›
The Hitachi Zosen EPBM was lowered down the launch shaft in August and assembly works are underway beneath the road deck. Excavation works ...
Thursday, 13 October 2016

Marina South Excavation (IV)

›
Excavation works are nearly completed at the S5-S6 layer across the 20m deep station box and cut and cover tunnel. Excavation works ac...
‹
›