Monday, 5 September 2016
S-893 Reassembly
›
Having completed the Changi Bound tunnel from LS2 to Woodlands, the re-assembly of S-893 (TBM 1) is taking place at LS1 for the RT3 tunnel ...
Sunday, 4 September 2016
Woodlands South Excavation (II)
›
The diaphragm wall for the southern zone of the station box and entrance A have been completed and excavation works are underway here. Bulk...
Saturday, 3 September 2016
Woodlands Excavation (V)
›
Bulk excavation works for the station box have reached the S5 layer and is nearing the formation level. Bored pile works are still being don...
‹
›