Monday, 25 May 2015
CREG TBM - Factory Acceptance
›
The first of 2 slurry TBMs manufactured by CREG for the Thomson Line has just passed its Factory Acceptance test last Thursday. The machine...
Friday, 15 May 2015
DCM Collapse at Marina South
›
One of the Deep Soil Mixing rigs collapsed at the Marina South station site earlier this evening. Works at the T227 site have been temporar...
Wednesday, 13 May 2015
Herrenknecht TBM - Factory Acceptance
›
The third Herrenknecht Mix-shield tunnel boring machine for the Thomson Line, which had been ordered by Sinohydro under the T217 project, h...
‹
›